I used a different method which I will mention here just it case it may be
helpful for a TT reader.
My qth is on irregular and jagged ledge – in some spots the ledge is at or just
below the surface (like an iceberg) in other spots, as little as 1’ away, the
dirt extends down for 4’ or more feet. You can’t predict where it is; you can
only dig and see where it actually lies.
My house sits in a small “valley” about 10 – 15’ below the top of the ledge
which starts less than 15’ from the ends of the house. Coming from the street
down my driveway facing my house, you could almost imagine this as a “U” with
the middle part of the “U” flat and very elongated.
Both of my towers are on the top of the ledge with no way to get there other
than to climb up at a very steep angle > 30 degrees. This made it impossible
to get a large concrete truck, with 20’ sq yds of concrete, up to the tower
base. And even if it made the first base, it could never get through the dense
woods and over the boulders to get to the second base 110’ feet away. It was a
challenge.
I decided to hire an experienced person with a SMALL backhoe. We proceeded by
having the large concrete truck drive to the base of the ledge, extend its
concrete pouring chute to the top of the ledge and then pick up that chute and
place it in the “scoop” of the small backhoe. (We had discovered that only a
small backhoe could navigate the boulders and jagged ledge (although not
without tearing and blowing out two backhoe tires in the process!)) The
concrete truck then poured the concrete through the chute into the scoop of the
backhoe filling it ~ 1/2 way. The chute was taken out and the backhoe
proceeded VERY slowly with the sloshing concrete and then poured it into slowly
and carefully into the tower base and guy anchor holes (already strengthened
with a cage or rebar and metal ties – previously made by N1MM and myself). At
each hole another employee of the concrete company worked with a concrete
trowel, level and other tools to move and spread the concrete and level it
properly. We repeated this process many times over a 2 1/2 hour period so
that we could fill in both tower bases and six guy anchor holes.
It was a slow and painstaking process but it produced outstanding results. No
concrete was lost or spilled, the concrete filled all the holes and spread and
leveled beautifully and the highly complex and challenging terrain was
overcome. We even had ~ 1 yard of concrete left over which I had them dump
into a depression in the driveway over an underground stream and which
successfully filled and stabilized a mini-sinkhole. :-)
This was in 1998 and cost ~ $1,050 cash for all the concrete, delivery, labor
and 1/2 hour of overtime. I had calculated that doing it all myself with
renting a mixer, buying all the concrete mix, and other chemicals, would have
cost at least $400 and consumed at least two full days. I’m not sure if it
would even have been possible to get the mixer through the woods and over the
boulders to the two tower bases, and guy anchor holes on the ledge in the
forest, but I do know that the labor would have been backbreaking – probably
almost as bad as the weeks of chainsawing that I had to do in order to clear
the dense forest for the tower locations. I know that I would not have had
results as good as having the professionals do it. There has been no issue with
any of the concrete in the past 21 years.
I would also add that the pros know the temperature range that the concrete
will set best at as well as the chemical composition of the concrete to give
the best “pour” and “set”. I certainly would not have known that. For that
information and knowledge alone to ensure the safety and the longevity of my
installations, it was worth every penny!
73
Bob, KQ2M
From: k7lxc--- via TowerTalk
Sent: Monday, August 26, 2019 1:11 PM
To: towertalk@contesting.com ; xdavid@cis-broadband.com
Subject: Re: [TowerTalk] Concrete
> What size is your tower base?? In my opinion, mixing your own for a
typical tower base is not a cost effective undertaking unless you have some
insurmountable access issue that prevents you from bringing in a mixer truck.
I agree. I've poured dozens of tower bases and every base plan I've ever
seen calls for 3kpsi concrete. The labor involved in buying, transporting,
mixing and pouring a base yourself doesn't usually pencil out compared to
having it delivered.
And if there is an access issue, hire a line pump to get the mud in the
hole. It'll pump up to 400 feet which should solve most problems.
Cheers,Steve K7LXCTOWER TECH -Professional tower services for amateur and
commercial
_______________________________________________
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
|