Re: [TowerTalk] best way to seal concrete with cut off tower section

To: mike stokes <mike9v@gmail.com>
Subject: Re: [TowerTalk] best way to seal concrete with cut off tower section
From: Matt Lovewell <lovewell@gmail.com>
Date: Tue, 11 Jul 2017 18:29:31 -0500
List-post: <mailto:towertalk@contesting.com>
Non-shrink grout

> On Jul 11, 2017, at 1:41 PM, mike stokes <mike9v@gmail.com> wrote:
> 
> I am in the planning stages of replacing 95' of Rohn 25 with 100' of Rohn
> 45.  The 25 has the bottom section concreted in.  I plan on drilling and
> epoxying a pier pin for the Rohn 45.  When I cut it off the 25, the holes
> in the legs will be exposed.  What is the best method to seal the leg holes
> to ensure they don't get water in them and freeze ?
> 
> Thanks in advance.
> 
> -- 
> Mike Stokes
> KK9V
> _______________________________________________
> 
> 
> 
> _______________________________________________
> TowerTalk mailing list
> TowerTalk@contesting.com
> http://lists.contesting.com/mailman/listinfo/towertalk
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>