This is what i did when specs called for a 4 ft. hole 8 ft deep. Cheaper than a backhoe and save $$$ on concrete. Check out pics at http://www.na5q.us/na5q/tower_installation.htm Roland
I will be starting a tower project in about a month. It will be a 72 FT crank-up and the specs call for a foundation that is 5ftx5ftx8ft. Is it reasonable to expect a back-hoe operator to be able to dig this size hole without elongating it beyond 5ftx5ft? Pat, K8PC _______________________________________________ See: http://www.mscomputer.com for "Self Supporting Towers", "Wireless Weather Stations", and lot's more. Call Toll Free, 1-800-333-9041 with any questions and ask for Sherman, W2FLA. _______________________________________________ TowerTalk mailing list TowerTalk@contesting.com http://lists.contesting.com/mailman/listinfo/towertalk |
| <Prev in Thread] | Current Thread | [Next in Thread> |
|---|---|---|
| ||
| Previous by Date: | [TowerTalk] Hole Digging Respnse and Thanks, Pat Chiles |
|---|---|
| Next by Date: | RE: [TowerTalk] Tower/mast/antenna height -- a clarification, Lou Laderman |
| Previous by Thread: | Re: [TowerTalk] Hole Digging Question, Alan C. Zack |
| Next by Thread: | Re: [TowerTalk] Hole digging question, Julio Peralta |
| Indexes: | [Date] [Thread] [Top] [All Lists] |