Re: [TowerTalk] Rebar Cage for Foundation

To: towertalk@contesting.com
Subject: Re: [TowerTalk] Rebar Cage for Foundation
From: Patrick Greenlee <patrick_g@windstream.net>
Date: Thu, 4 May 2017 21:27:29 -0500
List-post: <towertalk@contesting.com">mailto:towertalk@contesting.com>
One solution for fit I have used was to make a jig by assembling some steel parts to the tower portion of the interface and then using that as a sort of go-no go gauge (transfer standard?) to adjust the cage components. The idea was that things equal to the same thing are equal to each other. I got a very snug virtually perfect fit.

Patrick        NJ5G


On 5/4/2017 12:20 PM, Joe Cucuzza wrote:
I had a local welding shop make mine, for an old Tri-Ex.
The shop used steel rod and welded each junction.
My understanding is that if there is a gap in a junction, lightning can arc
and cause problems.
I also suggest taking the bottom section of the tower to the welder, so
that the fit will be as close to perfect as possible.
73
Joe KA8WEP

On Thu, May 4, 2017 at 11:37 AM, Joe Partlow <joe.w6jwp@gmail.com> wrote:

I need to pour a base for a TMM-433HD tower but first I need a rebar cage.
Do it myself or hire someone and who would I hire?

--
- 73 -
- Joe W6JWP
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>