When I lived in Dallas some 15 years ago I was given a damaged TX472 
tower by a friend who was moving to another state. It was folded over in 
the 2nd section from the top. I believe it had supported a TH6 and a 
shorty forty. He said he had a small tornado come through doing the 
damage I  do not know the mast situation. He had hack sawed the tower 
off at the bent area. There was a very slight bend in one of the corner 
tubes just above the attachment point at the base. I ordered a new 
section 2 from UST and replaced the damaged one. I drove a steel bar a 
couple of feet long up into the bent leg. This repaired tower supported 
a 10-15-20 meter stack for 5 years with no problems. When I moved to 
Washington I brought the tower and it now supports a 4el 20/ 2el 40 
interlaced F12 yagi and has given no problems in the 10 years up here.

73, Dan, N5AR

Steve, W3AHL wrote:
> Kevin,
>
> Based upon your assumptions and rough estimates, you are correct that the top 
> section in your example would be operating near its max stress limit with the 
> rated load at the top of the tower and adding a mast load based upon an 
> "Equivalent Moment" at the tower base  would result in failure of the top 
> section.
>
> But without seeing the manufacturer's spec's & stress analysis or doing one 
> from scratch, it's hard to know if your assumptions and estimates were valid. 
>  
>
> If you have the HG-72HD stress analysis that shows the max bending moment for 
> the top section joint is 7368 ft-lbs, why extrapolate anything from an 
> uncertain 25G spec?
>
> A spreadsheet with "per section"  limits shouldn't be necessary if you have 
> the manufacturer's stress analysis, since it should give the calculated 
> combined stress / maximum allowable stress ratio for each section (F.S.).
>
> Steve, W3AHL
>
> Date: Sat, 20 Mar 2010 09:04:10 -0700
> From: Kevin Normoyle <knormoyle@surfnetusa.com>
> Subject: [TowerTalk] comparing top section of crankup to unsupported
> 25g (and effects of long mast)
> To: Tower Talk List <towertalk@contesting.com>
>
> Thanks for the thoughts on analysis. sounds like some folks were 
> interested in this, so here's what I was thinking when I said I wasn't 
> confident  analyzing the moment limit at the base was sufficient
>
> I can't help thinking that the top section of crankups is similar to 
> looking at unsupported 25g.
> I am no PE, just trying to understand what I should worry about and what 
> I shouldn't.
>
> If we just had a little database of max bending moment for different 
> crankup tower sections, we could expand spreadsheets like Travanty's to 
> do "per section analysis"
>
> Steve is probably right abuot which section typically has least 
> margin...but here's a quick swag just thinking about the top section, 
> and what happens if you put a long mast up.
>
> Rohn 25g is 12" o.c. tubes right? Very similar to many top sections of 
> crankups. (US tower is 13" o.c. tubes?)
> So a very rough estimate would be comparing a top section behavior, with 
> a long mast, to unsupported 25g with a long mast.
>
> I found I think on towertalk, a claim that Rohn spec'd max bending 
> moment of 6720 ft-lbs for 25g.
>
> Let's look to see if the wind load due to the top section itself is 
> significant:
> If we say .29 sq ft of wind load per ft, and 17 feet of top section 
> above the last joint, then there's the equivalent of maybe 1.2 sq ft of 
> point windload at 1 ft above the top, just due to the wind on the top 
> section. (equation not shown). Seems small, so let's ignore for now.
>
> So taking the max moment 6270 and dividing by 17+1 feet, (since people 
> spec a wind load 1 ft above the top, and taking away the overlapped top 
> section (about 3') ) we get
>
> 6720 ft-lbs/18 ft = 373 lbs (horizontal) allowed 1 ft above the top section.
> For comparison, on my HG-72HD analysis, it appears that if I take the 
> numbers on compressive load limits on the vertical tubes of the top 
> section, they imply a 7368 ft-lb limit for max moment at the joint..so 
> I'm in the right ballpark. Also it appears compressive load limits on 
> the vertical tubes might be the limiter? (there were other failure modes 
> analyzed).
>
> At 60 mph...12 lbs/sq ft of wind load? (I may be off there)...so 373/30 
> -> it makes sense they spec 30' sq ft of wind load at 1' above the 
> tower, for a US Towers HDX say, with 13" o.c. top section ...I'm just 
> making rough estimates here.
>
>
> Now what happens if you put a infinitely strong mast, so that you put 
> that wind force 12' higher?
> 18 + 12 = 30 feet
> 6720 ft-lbs/30 feet = 224 lbs allowed. So at 60 mph, that's 18 sq ft of 
> antenna allowed (at the end of the mast)
>
> Adding 12 ft to a 72 ft tower, isn't much of an increment, if you're 
> calculating the moment at the bottom.
> Adding 12 ft to a 17 ft section (distance from the last joint), is 
> significant, if the last section is the limiter.
>
> So what's my point: Sure if you think you're cranking down your tower in 
> big winds, and that's how you get away with a big mast and big loads, 
> and you need the strong mast to survive when the tower is down.
>
> But if the tower is up, the top section is quickly at risk with a long mast.
> But if the tower is down, it's fair to look around at trees and house 
> and get a more reasonable peak wind estimate.
>
> ..snip..
> _______________________________________________
>
>
>
> _______________________________________________
> TowerTalk mailing list
> TowerTalk@contesting.com
> http://lists.contesting.com/mailman/listinfo/towertalk
>   
> ------------------------------------------------------------------------
>
>
> No virus found in this incoming message.
> Checked by AVG - www.avg.com 
> Version: 9.0.791 / Virus Database: 271.1.1/2760 - Release Date: 03/20/10 
> 12:33:00
>
>   
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>