Absent an engineering analysis that what you're proposing will be adequate, and
that the streeses from the guys won't compromise the structure, I wouldn't
deviate from the manufacturere's engineered foundation requirment. Too
dangerous.
Lou
-----Original Message-----
>From: Bert Almemo <balmemo@sympatico.ca>
>Sent: Aug 12, 2008 8:32 AM
>To: towertalk@contesting.com
>Subject: [TowerTalk] Installing HG52SS
>
>Hi guys,
>
>I'm preparing to install a Telex-Hygain HG52SS, 3 section, 52ft,
>crank-up/tilt over, tower. This is a self-supporting tower if you make the
>base 3'x 3'x 6'. Windload 9.5 sq.ft.
>
>I want to make a less permanent installation as we may be out of this place
>in a couple of years. Therefore I was thinking of making the base approx.
>2'x 2'x 2' and guy the bottom section (3 or 4 guys) at 20 ft. I'm going to
>use screw anchors for the guy wires. Sandy soil. Windload approx. 15 sq.ft.
>
>Ideas and comments greatly appreciated. Thanks.
>
>73 Bert, VE3OBU
>
>
>_______________________________________________
>
>
>
>_______________________________________________
>TowerTalk mailing list
>TowerTalk@contesting.com
>http://lists.contesting.com/mailman/listinfo/towertalk
_______________________________________________
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
|