Good Day
I would like to get some input on 2 questions regarding tower grounding. I
have read the Polyphaser TD1016 but do not find clear answers
1) Can the tower grounding system be put BELOW the tower BEFORE the
concrete is poured?
2) What is the best configuration for this grounding - 4 rods with a
star configuration where one rod is put in the one corner with straps to
each of the rods in the other corners? Or just link the 4 rods up in a
square configuration?
I am using 3mm x 20mm copper flat bar for connecting the rods.
Your input will be greatly appreciated
73
Marinus Willemstijn
ZS6MAW