Ted:
At 24-48 hours it may be OK to bolt the tower to the concrete base,
but don't crank up the tower to its raised position. The concrete takes a
while to cure to its ultimate strength. The last time this question was
asked here, most of the responses advised waiting 2-4 weeks before you load
the concrete with anything beyond dead weight like a lilted-over tower.
73 de
Gene Smar AD3F
----- Original Message -----
From: "Joe - WDØM" <WD0M@centurytel.net>
To: <k2qmf@juno.com>; <towertalk@contesting.com>
Sent: Sunday, November 14, 2004 11:10 AM
Subject: Re: [TowerTalk] Concrete Base?
Check with your concrete company and get their advice - I had 4000 psi
delivered and poured, and the company recommended 24 hours to cure
sufficiently - I waited 48 to be safe. No problems.
73,
Joe
WDØM
At 08:49 AM 11/14/2004, k2qmf@juno.com wrote:
Hello All,
I have a question regarding tower base concrete.
How long should concrete cure after pouring to
be safe to install a crank-up, tilt over tower???
The mix is 3500 psi.
Many Thanks in advance. 73, Ted K2QMF
_______________________________________________
See: http://www.mscomputer.com for "Self Supporting Towers", "Wireless
Weather Stations", and lot's more. Call Toll Free, 1-800-333-9041 with any
questions and ask for Sherman, W2FLA.
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
_______________________________________________
See: http://www.mscomputer.com for "Self Supporting Towers", "Wireless Weather Stations", and lot's more. Call Toll Free, 1-800-333-9041 with any questions and ask for Sherman, W2FLA.
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk