Hi, all; David Robbins mentioned free-fall. To add detail, free-fall and excessive vibrating or stirring causes the aggregate to separate. The large pieces go to the bottom, the fines, including the cement, separate and rise to the top. The result is not a homogeneous mixture of aggregate and cement and its strength is not uniform. Confer with a knowledgeable professional regarding the limits. 73 de WOØW _______________________________________________ See: http://www.mscomputer.com for "Self Supporting Towers", "Wireless Weather Stations", and lot's more. Call Toll Free, 1-800-333-9041 with any questions and ask for Sherman, W2FLA. _______________________________________________ TowerTalk mailing list TowerTalk@contesting.com http://lists.contesting.com/mailman/listinfo/towertalk |
Previous by Date: | Re: [TowerTalk] The tower base is poured BUT..., Robert Shauger |
---|---|
Next by Date: | [TowerTalk] Rotator survey redux, UpTheTower |
Previous by Thread: | Re: [TowerTalk] The tower base is poured BUT..., Jerry Keller |
Next by Thread: | Re: [TowerTalk] The tower base is poured BUT..., Jim White, K4OJ |
Indexes: | [Date] [Thread] [Top] [All Lists] |