80m + Rohn 25 in swamp = HELP!

Subject: 80m + Rohn 25 in swamp = HELP!
From: H. Ward Silver" <hwardsil@seattleu.edu (H. Ward Silver)
I would think that there might some serious settling problems once the
base is poured.  Can you get to a firm soil layer within 6-feet of
surface?  It might a REAL GOOD idea to check with a contractor or soils
engineer for a little advice (not necessarily a soils/footing design)
about the ability of the subsurface material to support the load. 
Otherwise, you might see your tower sink slowly into the ooze...not kidding!

73, Ward N0AX (son of an expert soils engineer who saw too many disasters
on field trips with Pop)