 Just to add to the discussion:

I had (some thing you can make in concrete) a 6 x 6 foot granite plate, 8 inch 
think. I drilled holes in it and attached six angle iron to it. I had a guy 
with a back hoe to bury it 5 feet below ground and filled back the dirt over it 
Left was the angle irons surrounded by cement. The irons were, two by two 
attached to the tower legs with the same bolts that were used further up the 
tower. I believe the advantage of this design is that it require lot less with 
cement/concrete and you don't have to look around where to put the 
'left-overs'. This holds a 85 foor alu tower. (To tower weigh ~#300) Just an 
other penny.

Hans - N2JFS

 

 

-----Original Message-----
From: Bryan Swadener via TowerTalk <towertalk@contesting.com>
To: towertalk <towertalk@contesting.com>
Sent: Fri, Mar 4, 2016 12:59 pm
Subject: Re: [TowerTalk] Foundation and ReBar Work

In 2012, I installed a new-to-me US Tower TX-472. I had a contractor dig the 
hole using a combination of manual labor + backhoe. The backhoe operator didn't 
hear/understand the word "STOP!", and the hole became extra wide & deep. As it 
turned out, extra deep was good because it allowed me to backfill with 1-1/2" 
round rock (that worked against the high water table). I sank a sump pump into 
the rock and kept the hole pumped out. I'm into that work for $1000.Rebar cost 
me $200 from a ham friend who is an "artiste" with the stuff. Some sticks of 
wood allowed us to lower it into the hole.Concrete cost me $1500 for 5000 psi 
mix. That included rental of a horizontal line pump. That was coordinated 
through a carpenter/contractor/ham friend. "Rebarman" brought and used his 
vibrator.There were many other costs involved but, IMO, none were suspiciously 
high. All things considered, I saved a lot of dough. vy 73,Bryan WA7PRCPhotos + 
text: http://www.tinyurl.com/wa7prc-tower      Date: Fr
 i, 4 Mar 2016 16:43:37 +0000 (UTC)From: Russ K5ZZRTo: Tower TalkSubject: 
[TowerTalk] Foundation and ReBar WorkI installed my new 72' US Tower last year 
and did the work myself including picking it up in Kansas. The 5'x5'x8' hole 
was dug for $450 which included spreading the dirt at various places on my 5 
acres. I was surprised at how accurate it was also, those guys are good. The 
rebar I would guess was about $150. The cement cost about $750 so the total 
must have been near $1,200. No other cost were incurred because I was not in a 
city. I finished the cement myself with the help of the cement truck 
driver.Russ K5ZZR   
______________________________________________________________________________________________TowerTalk
 mailing 
listTowerTalk@contesting.comhttp://lists.contesting.com/mailman/listinfo/towertalk
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>