Re: [TowerTalk] TOWER BASE CREATION

To: towertalk@contesting.com, bclifton@neb.rr.com
Subject: Re: [TowerTalk] TOWER BASE CREATION
From: K7LXC@aol.com
Date: Sun, 25 Jan 2009 15:29:41 EST
List-post: <towertalk@contesting.com">mailto:towertalk@contesting.com>
 
In a message dated 1/25/2009 8:30:04 A.M. Pacific Standard Time,  
towertalk-request@contesting.com writes:

>  Situation
I have been given an 8 section tower.  1/2  of the bottom section is cemented
into the base.  We will take the  tower top seven sections down, then saw off
the legs of the bottom section  at the cement base.

>  Question
Was this an approved method  of installing a tower?  Will it be better to
purchase the three  factory legs to place into the cement base. 


    This is a technique used by hams all the time and  the only downside is 
that the tower gets shorter over time each time you cut  it off and move it. 
Feel free to do the same thing with no problems. 
 
Cheers,
Steve   K7LXC
TOWER TECH 





**************From Wall Street to Main Street and everywhere in between, stay 
up-to-date with the latest news. (http://aol.com?ncid=emlcntaolcom00000023)
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>