Skip.. I actually came up with 21.33 cu yrd (7.1 x 3) but whose counting :)


I just poured (9-18-09) a 5x5x6 for a TX-455 and the cost was $84.50 per
yard (4000#) plus $4.00 each for fiber added. Then 6% sales tax for
Kentucky. The concrete company had a 4 yard min and also added $10 fuel
charge

3500# was a dollar less per cu yard

Anway..good luck with the project.. I plan on a 60' 25g later this year or
spring and will have to elevate the guys also


73

John
KO4XJ
www.w4nja.org/ko4xj.htm






-----Original Message-----
From: towertalk-bounces@contesting.com
[mailto:towertalk-bounces@contesting.com] On Behalf Of Skip K3CC
Sent: Monday, September 22, 2008 5:30 PM
To: towertalk@contesting.com
Subject: [TowerTalk] Raised guys

Ok, you talked me out of raised guys.  My system would work however, I just 
did the cost of concrete @ 100/yard.  Each deadman was 4ft deep in a 6 X8 ft

hole. That would require a min of 25 cu.yds of concrete.

I just won't cut most of the weeds under the tower in the field, only near 
the base.

de Skip  K3CC 

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>