In a message dated 12/4/2007 5:45:18 P.M. Pacific Standard Time,  
towertalk-request@contesting.com writes:

>  My concrete guy gave me a fixed-price quote for the hole for  my HDX-555. 
The hole was supposed to be 5x5x7 but ended up significantly  larger, so 
he simply poured more concrete: 9yds instead of 6.5. Perhaps he  had 
already allowed for that possibility when he quoted, but I still paid  
only what he quoted.
 
    When it comes to excavation, my experience has  been they come out bigger 
all the time - I'd say 80-90% of the time. Backhoes  are not precision 
implements and then you have soil problems with sloughing.  Your experience is 
pretty typical. Shame on your contractor for  underestimating the job. 
 
    OTOH I did a job in Oregon where we removed 8 or  so yards or dirt and 
there wasn't a single rock in it. And the sides were  totally plumb. It was 
beautiful. And easy for a change.
 
Cheers,
Steve    K7LXC
TOWER TECH 



 



**************************************Check out AOL's list of 2007's hottest 
products.
(http://money.aol.com/special/hot-products-2007?NCID=aoltop00030000000001)
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>