In a message dated 8/10/2007 7:53:29 P.M. Pacific Daylight Time,
towertalk-request@contesting.com writes:
> Thank you all for the advice. Seem like most believe doing in "smaller
bites" is the way to go. Since the first set of guys are at 31' and the
second are at 61', top at 94' . I am now think of lifting the first 7
sections (70ft) thereby permitting 2 guy levels to be anchored before
raising the last 30ft of the Rohn 45g.
Why make 2 lifts when you can make 1?
> The negative seems to be more crane time and not being able to run the
coax
on the tower before the lift.
That's NO negative. See, you're already trying to violate my admonition
to only do one thing at a time. You do the cables later.
> I am still likely to have the rotor and mast in the 30ft lift.
Sure. If you put the whole tower up at once, you still have to bring the
mast up so either way you've got 2 lifts. Six of one, half-dozen of the
other.
Cheers,
Steve K7LXC
TOWER TECH
************************************** Get a sneak peek of the all-new AOL at
http://discover.aol.com/memed/aolcom30tour
_______________________________________________
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
|