Three sections of unguyed 45G is the norm during tower erection.  A little 
tippy but very do-able and safe.  As far as temp guys, you may not need them 
depending on your tower base.  If the base is imbedded in concrete, I'd just 
erect the first three sections and then you're at your first guy point.

My tower uses the tapered, pier pin base.  So what we did was to install that 
section and the next section and using a bunch of guys, Iwo Jima-ed that up 
into position.  My main climber had brought his temporary guys which were 
Circus tent rope and metal poles.  This was the big stuff.  Each leg had to 
rops coming off of it to stakes securely pounded into the ground.  This two 
section piece was secured and left alone and then up we went, gin-poling the 
tower up to 120 ft.

Piks on my website below.


--
Phil - KB9CRY 
Lockport, IL 
http://nidxa.org/memberWWW/kb9cry_home.htm
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>
  • [TowerTalk] TowerTalk] temporary guys, Phil Camera <=