Re: [TowerTalk] CONCRETE CURING

To: TOWER TALK <towertalk@contesting.com>
Subject: Re: [TowerTalk] CONCRETE CURING
From: Chris Bolton <cbolton@gtmc.net>
Reply-to: cbolton@gtmc.net
Date: Mon, 28 Aug 2006 21:23:23 -0500
List-post: <mailto:towertalk@contesting.com>
I have built many towers ranging from 50' to 350' and the compression 
tests always test bad at a week and great after 3 to 4. If it was me I 
would wait at least 3.
Chris

Craig Clark wrote:
> Most builders will cap a foundation within a week of a pour.
> 
> Lots of them  will start framing at the same time. My sense is a week 
> is good enough.
> 
> 
> 
> 
> 
> 73, Craig Clark, K1QX
> 
> 
> RADIOWARE AND RADIO BOOKSTORE
> PO  BOX 209
> RINDGE NH 03461
> 603 899 6957
> WWW.RADIO-WARE.COM
> 
> 
> 
> _______________________________________________
> 
> 
> 
> _______________________________________________
> TowerTalk mailing list
> TowerTalk@contesting.com
> http://lists.contesting.com/mailman/listinfo/towertalk
> 
> 

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>