I would say one week is not enough, remember the compression/tension from a
tower in wind is a lot more stressful than foundations.  I think you are
guessing, the people who poured my concrete said they always recommend 3 to
4 weeks for towers or longer for complete curing.

Mike


Most builders will cap a foundation within a week of a pour.

Lots of them  will start framing at the same time. My sense is a week 
is good enough.





73, Craig Clark, K1QX


RADIOWARE AND RADIO BOOKSTORE
PO  BOX 209
RINDGE NH 03461
603 899 6957
WWW.RADIO-WARE.COM



_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>