I almost hate to reply, because there will be so much
said about this that I am sure some will think me totally
wrong, but, let the flames begin.
Weld up the split, checking the remaining legs carefully
for any more splits. Make a weep hole at the base of each leg,
so that water cannot pool again, and be sure to clean them
yearly.
Put a piece of angle opposite the split, stretching 2 feet
above and below the split. Take a number of
u-bolts, clamp them down well, and either punch the
threads to that the bolts cannot back off, or spot weld
them. Prefered stainless hardware, or galvanized.
>I have a 95' Rohn 25 tower, guyed at 3 levels. While
> mowing today I discovered a 1" slit, 1/16th wide, in
> one of the legs of the bottom section, about 28" above
> the 4'deep concrete base.
> Can this be salvaged? Any ideas on what might have
> caused this?
> Thanks in advance for any advice.
>
_______________________________________________
See: http://www.mscomputer.com for "Self Supporting Towers", "Wireless Weather
Stations", and lot's more. Call Toll Free, 1-800-333-9041 with any questions
and ask for Sherman, W2FLA.
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
|