>I will be starting a tower project in about a month. It will be a 72
FT
>crank-up and the specs call for a foundation that is 5ftx5ftx8ft. Is
it
>reasonable to expect a back-hoe operator to be able to dig this size
whole
>without elongating it beyond 5ftx5ft?
>Pat, K8PC
_______________________________________________
>>----- Original Message -----
>>From: "Dave NØRQ" <n0rq-1@dfwair.net>
>>To: "Pat Chiles" <chilesp@adelphia.net>; <towertalk@contesting.com>
>>Depends on the machine he uses, and his skill.
>>If the backhoe is large (or maybe even mid-sized),
>>it makes it harder.
_______________________________________________
Not necessarily. I had two tower holes 4x4x8 dug by a huge backhoe.
This backhoe had a telescoping arm that would go straight out from
the pivot arm with the result that the bucket could go straight down.
Most backhoes don't have a telescoping arm.
The size of the hole also depends on the soil as the hole may be
enlarged due to cave-in(s).
BTW, I have owned a small Kubota tractor with small backhoe for
about a year and I definitely agree that a lot depends on the operator
skill and how fast he tries to dig the hole. The bucket on my backhoe
will not rotate up enough to allow digging a straight vertical wall very
deep.
I was charged $60/hr with a two hour minimum. The holes were dug
in much less than the minimum time. Even with owning a small
backhoe, I would pay the $120 if I had to dig more big holes. Where are
you going to put the dirt? The operator will move it around for you
during the minimum time.
Hope this helps
k7puc
_______________________________________________
See: http://www.mscomputer.com for "Self Supporting Towers", "Wireless Weather
Stations", and lot's more. Call Toll Free, 1-800-333-9041 with any questions
and ask for Sherman, W2FLA.
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
|