        You said that you are going to be mixing all of this in a mixer.
This is a lot of work even for a large portable mixer.  Not to mention the
strain on your back.  You will be moving close to 6 1/2 tons of material.
For the 4 yards of concrete delivered, it would come close to $300 depending
on your local rate.  Considering the consistency of the mix you could
produce in the required time and the labor involved.  Why don't you just get
the ready mix?



You should have the following approximate weights.

3/4" Aggregate
aggregate       64 lbs/cu ft    1728 lbs/cu yd  6152 lbs for your job
Sand    47 lbs          1269 lbs/cu yd  4518 lbs
Cement  23 lbs           621 lbs/cu yd  2211 lbs

Over 3 tons of Aggregate
Over 2 1/4 tons of Sand
Approximately 24 bags of cement

1/2" Aggregate
aggregate       56 lbs          1512 lbs/cu yd  5383 lbs for your job
Sand            49 lbs          1323 lbs/cu yd  4710 lbs
Cement  25 lbs           675 lbs/cu yd  2403 lbs

Over 2 1/2 tons of Aggregate
Almost 2 1/2 tons of Sand
Approximately 26 bags of cement



v/r,
Joe
AG4BW




The information contained in this e-mail message and any attachments is
confidential information intended only for the use of individuals or
entities named above. If the reader of this message is not the intended
recipient you are hereby notified that any dissemination, distribution or
copying of this communication is strictly prohibited. If you have received
this communication in error, please notify us immediately by e-mail at the
originating address.


-----Original Message-----
From: VeeAthreePL [mailto:va3pl@cuic.ca]
Sent: Monday, June 02, 2003 1:51 PM
To: towertalk@contesting.com
Subject: [TowerTalk] How to mix concrete in the mixer


I am just about (this coming weekend) pour my concrete base for TX455 
tower. Foundation for it is going to be 4 X 4 X 6 deep.
I'll be using a mixer to make the concrete (cement).
Can anybody tell me a proper ratio of Portland Cement to gravel.
How many pounds of portland I need?
I heard that I should use 1 to 3 ratio but I also hear that 1 to 10 is 
good enough.
Which one is correct?
What is the proper mix to get 3000psi concrete, then?
I think I ask too much!!!

73 to all Andy - VA3PL

_______________________________________________

See: http://www.mscomputer.com  for "Self Supporting Towers", "Wireless
Weather Stations", and lot's more.  Call Toll Free, 1-800-333-9041 with any
questions and ask for Sherman, W2FLA.

_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
<Prev in Thread] Current Thread [Next in Thread>
  • [TowerTalk] How to mix concrete in the mixer, Mowery Joseph D DLVA <=