In a message dated 5/4/01 10:18:41 PM Pacific Daylight Time,
eric_schurman@hotmail.com writes:
> I am going to be putting up about 90' of Rohn 25G tower and had a couple of
> questions about guying. This is going to be a temporary installation in a
> location which has a leave no trace policy.
Why don't you use regular anchors in concrete and then just cut off the
anchor rod when you leave? The concrete will be a couple of feet below grade
anyway and virtually undectable by anyone in the future. There will be "no
trace".
Cheers, Steve K7LXC
Tower Tech