Towertalk
[Top] [All Lists]

[TowerTalk] Rebar cage question

To: <towertalk@contesting.com>
Subject: [TowerTalk] Rebar cage question
From: clintone@worldnet.att.net (Clint Heffner)
Date: Tue, 02 Nov 1999 11:48:26 -0400
Hello.
On page BX-9 of the Rohn Consumer Catalog it says No.3 Bars, 12" on
center eachway top and bottom.
I know what #3 bars are and understand 12" o.c. but does this means you
have a frame 3 inches below the surface and then a frame 3 inches above
the bottom of the concrete which are not hooked together?

Are all the bars horizontal or are there supposed to be vertical ones?

Thanks.

Clint -- kf8mz



--