> How long do you wait after pouring tower base and guy anchors for the
concrete
> to come to strength before proceeding with the remainder of the
installation?
>
The concrete reaches over 80% of its ultimate strength within 2-3 weeks
and is considered to be cured after 28 days having reached its specified
strength.
If you're in a real hurry, 7-10 days is about the minimum although it's
not recommended. After 2 weeks it's strong enough for most ham-type
installations.
73, Steve K7LXC
--