A rebar cage is not rocket surgery or brain science! To give you better advice you need to give some details on the tower to rebar cage connection. There are several methods of connecting the concrete to the tower base. My Tashjian 70 foot crank-up/tilt-over has bar stock protruding vertically downward from all three legs of the tower. The bar stock is 3 inches wide and each of the 3 pieces of bar has 6 holes on 2 1/2 inch centers. Similar steel bars with matching holes for 3/4 inch bolts are set in concrete and bolt to the tower. The bars in the concrete are welded to the rebar cage.

Having fairly recently become a "bionic man" (pacemaker defibrillator) I'm not supposed to weld so bought the cage built from Tashjian (excellent materials and workmanship) but if I had it to do over I would have hired a local welder to do the welding and I would have done the assembly in prep for that myself. My foundation (as per Tashjian drawings) is 4'x4' square and 8 ft deep. I formed up an 8x10 ft rectangle centered on the 4x4 hole using 2x6 lumber (5 1/2 inches wide) to give me extra tilt resistance and a nice place to stand when doing anything at the tower base. I used significant quantities of rebar to tie the 8x10 slab to the 4x4 central core of the composite foundation.

There are numerous other tower to foundation designs. To offer additional assistance I think most of us here would need more info about your specific tower mating system to be able to give actionable advice. I am happy to offer more assistance if you can supply more details and maybe someone else has some good ideas for you too.

If you don't weld and have no access to a good welder then buy the cage pre-built.

Patrick        NJ5G



On 5/4/2017 11:37 AM, Joe Partlow wrote:
I need to pour a base for a TMM-433HD tower but first I need a rebar cage.
Do it myself or hire someone and who would I hire?


_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>