In a message dated 98-04-06 20:33:48 EDT, mowery@shianet.org writes:
> Am currently in the process of putting up a Rohn HDBX-48 tower with BXB-8
> concrete base stubs. What's the best way to insure all 3 stubs are
installed
> at the right height so the tower will be plumb? It's been suggested that I
> attach them to the bottom tower section, suspend the whole shebang over the
> hole at the right height and use a level on the tower itself. That makes
> sense, but does anyone have any tricks they'd care to pass along? How did
you
> do it?
That's how you do it - sounds good to me.
Cheers, Steve K7LXC
--