| We (K7LXC & I) ended up finding a unknown buried abandoned septic tank 
for my HDX589 base.  Moved over 5' and found a second one!  Concrete 
without rebar is legal structural fill so the humongous hole sucked up 
19 yards vs the 9 yards for the UST design.  Use a form to make it look 
good above ground and pour to have 6" of topsoil over the fill concrete. 
Grant KZ1W
On 10/25/2014 2:19 PM, David Gallatin via TowerTalk wrote:
 
Hello everyone.  When last we spoke I was off to dig my hole. 36×36×48. At the 
top I have a slope of about ten degrees to the east. I'm about done but I have not 
decided what, if anything to do about the slope. I'm going to level the bottom which I 
estimate will mean going to 50 inches on the west side. So long as the bottom is level do 
I need to concern myself much with the top? FYI...digging sucks. Lol.
Sent from Yahoo Mail on Android
_______________________________________________
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
 
_______________________________________________
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
 |