Re: [TowerTalk] Tower Foundation Pad Removal

To: towertalk@contesting.com
Subject: Re: [TowerTalk] Tower Foundation Pad Removal
From: Patrick Greenlee <patrick_g@windstream.net>
Date: Sun, 17 Aug 2014 12:45:09 -0500
List-post: <towertalk@contesting.com">mailto:towertalk@contesting.com>
Another consideration is to leave the existing base in place and excavate a new hole next to it. Then drill and dowel into the old with rebar to add/bond the old to the new. If you don't fully trust this approach then make the new part full sized and not dependent on help from the old even though it will help quite a bit.

Patrick NJ5G

On 8/17/2014 12:27 PM, Kenneth Goodwin wrote:
As part of a tower replacement project, a possible plan is to remove the
existing foundation in one piece using an infinitely sized crane attached to
the tower anchor bolts.  The pad is 6.5 x 6.5 X 4 feet (6 cu yards
estimated).  An effort to break the dirt from around the foundation would be
attempted (water hose and some penetrating device inserted down the side of
the foundation pad).  The remaining hole would be used for the new
foundation installing new rebar as per Rohn SSV foundation drawings (Rohn
SSV tower, 60 feet using 6N, 5N and 4N twenty foot sections).  Any reason
not to consider this as a possible plan for the new tower foundation?

Secondary question: Do you tie the tower and the rebar into a ground
connection at the bottom of the foundation?  Years ago one isolated the
rebar but I think the thoughts today are just the opposite.

Ken K5RG

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk


_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>