Re: [TowerTalk] CONCRETE CURING

To: "W7CE" <w7ce@curtiss.net>, <towertalk@contesting.com>
Subject: Re: [TowerTalk] CONCRETE CURING
From: "Merlin-7 KI4ILB" <merlin-7@sc.rr.com>
Date: Tue, 29 Aug 2006 01:31:51 +0100
List-post: <mailto:towertalk@contesting.com>
 OK it looks like it will be 4 weeks, I will not be happy but I do take the
advise of people that know a lot more about this subject than I do. ( thats
why I ask)

 Thanks everyone
 73s Joe

 PS many more questions to follow. please be kind...


> The compressive strength of concrete is always based on 28 days of curing
> time.  If you specify 3500 PSI concrete, it will take 28 days of curing to
> reach that strength.  After 28 days, it will continue to get stronger.
> After 7 days of curing it will only have reached about 60% of its 28 day
> strength.  If you were to install your tower before the 28 days has
elapsed,
> it is possible that the concrete could be weakened by the premature
stresses
> that the tower puts on it.  This may or may not be visible by inspection.
> Do what the manufacturer says.  Let the concrete cure for 28 days minimum,
> and be sure to keep it wet during the curing process.  Cover it with
burlap
> or black plastic and don't let the surface dry out.  In spite of all
> anecdotal evidence to the contrary, play it safe and do it right.  It's
only
> 4 weeks.
>
> 73,
> Clay  W7CE
>
>
> _______________________________________________
>
>
>
> _______________________________________________
> TowerTalk mailing list
> TowerTalk@contesting.com
> http://lists.contesting.com/mailman/listinfo/towertalk
>

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>